Miami Valley Hospital – 10th and 11th Floors

Building better healthcare.

Client

Miami Valley Hospital
Skanska USA Building

Value

$2.6M

Role

General Trades Contractor

Location

Dayton, Ohio

Partners

PDT Architects (now Elevar Design Group)

The interior fit out of the tenth and eleventh floors of the Patient Tower at the main campus of Miami Valley Hospital in Dayton, Ohio. The two new patient bed floors included 72 patient rooms, nurse’s station, corridor hallway, elevator lobbies and restrooms.

Megen served as the general trades contractor, and our scope included wood blocking, headwall installation, cabinets and countertops, painting, flooring and wall tile. The schedule for the project was extremely tight with the build out of two floors in nine months. Megen’s project team coordinated with MEP trades to ensure the project remained on schedule, as we were completing the finishes, while MEP trades were still working above ceiling.

67,784

Square Feet

2018

Completion