Valley View Salt Dome & Conveyor

Facilitating salt delivery.

Client

City of Cincinnati

Value

$1.8M

Role

Design-Builder

Location

Cincinnati, Ohio

Partners

KZF Design, Inc.

The design and construction for replacement of the tensile fabric on the Valley View Salt Dome and installation of a larger 24” salt conveyor with a new hopper system in a pit with a pit shed for unloading the salt from semi-trucks into the salt dome. The project includes removing and reinstalling all lighting and exhaust systems, as well as replacing disconnects and electrical panels and conduits.

Megen served as design-builder for the City of Cincinnati, and was responsible for managing all facets of the project including design coordination, establishment of the overall project schedule, cost control, safety management and coordination with end user personnel. Megen completed the project in nine months, including design and construction activities, to meet the start of winter season salt deliveries.

18 tons

Project Size

2018

Completion